Hi all,
I'm just having a "before I make this change I want to make sure I'm not going to cause havoc" moment so I am asking for some clarification, apologies if this has been asked elsewhere as I couldn't find an answer to this scenario.
Currently we have a SCVMM 2012 setup which is managing a Server 2012 Cluster, I have just set up a new SCVMM 2012 R2 system and 2012 R2 cluster, tested and it is ready to go, currently we are running both systems and plan to run both for a few months.
My question is as we want to migrate machines from the old to the new cluster, am I ok just to add the 2012 cluster to the SCVMM 2012 R2 console for purposes of migration, will this cause any negative effects with the old SCVMM or the cluster itself?
I'm confident it wont, but as this is production and I don't have a test lab here I thought best to see if anyone else has done this to put both mine and my managers mind at ease.
Many thanks